Anchor Windlass Design and Testing (IACS 2018 Requirement)

Anchor Windlass Design and Testing (IACS 2018 Requirement)

2023-11-15     08:37

Introduction

Different types of machines are used on a ships deck for the overall and smooth functioning of deck procedures. Deck procedures such as cargo handling, berthing and anchoring represent a lion’s share of a vessel’s total working operations.

Design and Testing

A windlass used for handling anchors, suitable for the size of chain cable and complying with

the Classification Society’s criteria is to be fitted to the ship. The design, construction and testing of windlasses are to conform to an acceptable standard or code of practice. To be considered acceptable, the standard or code of practice is to specify criteria for stresses, performance and testing.

The following are examples of standards recognized:

  • SNAME T & R Bulletin 3-15:2018 - Guide to the Design and Testing of Anchor Windlasses for Merchant Ships
  • ISO 7825:2017 Deck machinery general requirements
  • ISO 4568:2006 Shipbuilding - Sea-going vessels - Windlasses and anchor capstans
  • JIS F6714:1995 Windlasses

Mechanical Design

Holding Loads

Calculations are to be made to show that, in the holding condition (single anchor, brake fully applied and chain cable lifter declutched), and under a load equal to 80% of the specified minimum breaking strength of the chain cable, the maximum stress in each load bearing component will not exceed yield strength (or 0.2% proof stress) of the material. For installations fitted with a chain cable stopper, 45% of the specified minimum breaking strength of the chain cable may instead be used for the calculation.

Inertia Loads

The design of the drive train, including prime mover, reduction gears, bearings, clutches, shafts, cable lifter and bolting is to consider the dynamic effects of sudden stopping and starting of the prime mover or chain cable so as to limit inertial load.

Continuous Duty Pull

The windlass prime mover is to be able to exert for at least 30 minutes a continuous duty pull

(e.g., 30-minute short time rating corresponding to S2-30 min. of IEC 60034-1), Zcont1,

corresponding to the grade and diameter, d, of the chain cables as follows:

Anchor Windlass Design and Testing (IACS 2018 Requirement)

The values of the above table are applicable when using ordinary stockless anchors for anchorage depth down to 82.5 m.

For anchorage depth deeper than 82.5 m, a continuous duty pull Zcont2 is:

Zcont2[N] = Zcont1[N] + (D – 82.5) x 0.27d2

or

Zcont2[kgf] = Zcont1[kgf] + (D – 82.5) x 0.0275d2

where

D is the anchor depth, in meters.

The anchor masses are assumed to be the masses as given in the Classification rules. Also, the value of Zcont is based on the hoisting of one anchor at a time, and that the effects of buoyancy and hawse pipe efficiency (assumed to be 70%) have been accounted for. In general, stresses in each torque-transmitting component are not to exceed 40% of yield strength (or 0.2% proof stress) of the material under these loading conditions.

Overload Capability

The windlass prime mover is to be able to provide the necessary temporary overload capacity

for breaking out the anchor. This temporary overload capacity or “short term pull” is to be at

least 1.5 times the continuous duty pull applied for at least 2 minutes. The speed in this period may be lower than normal.

Hoisting Speed

The mean speed of the chain cable during hoisting of the anchor and cable is to be at least 0.15 m/sec. For testing purposes, the speed is to be measured over two shots of chain cable and initially with at least three shots of chain (82.5 m or 45 fathoms in length) and the anchor submerged and hanging free.

Brake Capacity

The capacity of the windlass brake is to be sufficient to stop the anchor and chain cable when paying out the chain cable. Where a chain cable stopper is not fitted, the brake is to produce a torque capable of withstanding a pull equal to 80% of the specified minimum breaking strength of the chain cable without any permanent deformation of strength members and without brake slip. Where a chain cable stopper is fitted, 45% of the breaking strength may instead be applied.

Chain Cable Stopper

Chain cable stopper, if fitted, along with its attachments is to be designed to withstand, without any permanent deformation, 80% of the specified minimum breaking strength of the chain cable.


Electrical Systems

Electric Motors

Electric motors are to meet the requirements of the class society and those rated 100 kW and over are to be certified. Motors exposed to weather are to have enclosures suitable for their location as provided for in the requirements of the class society. Where gears are fitted, they are to meet the requirements of the class society and those rated 100 kW and over are to be certified.

Electrical Circuits

Motor branch circuits are to be protected in accordance with the provisions of the class society and cable sizing is to be in accordance with the requirements of the class society. Electrical cables installed in locations subjected to the sea are to be provided with effective mechanical protection.


Protection of Mechanical Components

To protect mechanical parts including component housings, a suitable protection system is to be fitted to limit the speed and torque at the prime mover. Consideration is to be given to a means to contain debris consequent to a severe damage of the prime mover due to over speed in the event of uncontrolled rendering of the cable, particularly when an axial piston type hydraulic motor forms the prime mover.

Couplings

Windlasses are to be fitted with couplings which are capable of disengaging between the cable lifter and the drive shaft. Hydraulically or electrically operated couplings are to be capable of being disengaged manually.


Shop Inspection and Testing

Windlasses are to be inspected during fabrication at the manufacturers’ facilities by a Surveyor for conformance with the approved plans. Acceptance tests, as specified in the specified standard of compliance, are to be witnessed by the Surveyor and include the following tests, as a minimum.

  • No-load test. The windlass is to be run without load at nominal speed in each direction for a total of 30 minutes. If the windlass is provided with a gear change, additional run in each direction for 5 minutes at each gear change is required.
  • Load test. The windlass is to be tested to verify that the continuous duty pull, overload capacity and hoisting speed as specified in above. Where the manufacturing works does not have adequate facilities, these tests, including the adjustment of the overload protection, can be carried out on board ship. In these cases, functional testing in the manufacturer’s works is to be performed under no-load conditions.
  • Brake capacity test. The holding power of the brake is to be verified either through testing or by calculation.

Each windlass is to be tested under working conditions after installation onboard to demonstrate satisfactory operation. Each unit is to be independently tested for braking, clutch functioning, lowering and hoisting of chain cable and anchor, proper riding of the chain over the cable lifter, proper transit of the chain through the hawse pipe and the chain pipe, and effecting proper stowage of the chain and the anchor. It is to be confirmed that anchors properly seat in the stored position and that chain stoppers function as designed if fitted.

The braking capacity is to be tested by intermittently paying out and holding the chain cable by means of the application of the brake. Where the available water depth is insufficient, the proposed test method will be specially considered.

Marking

Windlass shall be permanently marked with the following information:

  • Nominal size of the windlass (e.g. 100/3/45 is the size designation of a windlass for 100 mm diameter chain cable of IACS Grade 3, with a holding load of 45 % of the breaking load of the chain cable)
  • Maximum anchorage depth, in meters.
The Author, Admin
Admin
Marine Engineer & MarineTopics Journalism
Disclaimer
Although all possible efforts have been made to ensure correctness and completeness of the contents contained in this information service, MarineTopics is not responsible for any errors or omissions made herein, nor held liable for any actions taken by any party as a result of information retrieved from this information service